Englewood Cliffs Antenna Installation

K2 Communications Case Study

WNBC/WNJU Englewood Discone Antenna Installation

Draft prepared from K2 quotations dated March 31, 2025 and June 11, 2025. Items not documented in the quotations are marked “To Confirm.”

1. Project Overview

Project Name: WNBC/WNJU Englewood Discone Antenna Installation

Location: 100 West Forest Avenue, Englewood, New Jersey

Customer / Industry: WNBC / WNJU — Broadcast Television / Media

Project Type: Building-mounted communications antenna engineering, permitting and installation

Date / Year: 2025 — engineering phase quoted March 31, 2025; installation phase quoted June 11, 2025.

Primary K2 Services

☒ Antenna & Wireless Infrastructure

☒ Engineering, Permitting & Structural Modifications

☒ Tower Maintenance & Remediation

☒ Communications Equipment Decommissioning

☒ RF Cabling & Transmission Infrastructure

2. The Challenge

What did the customer need to accomplish?

As WNJU was going to be moving out of their Fort Lee location, they needed to establish communications antenna infrastructure at its new Englewood facility, prior to the decommissioning of the old site. This included antenna mounting, RF transmission lines, building entry, grounding and permitting.

The project began with an engineering site inspection and development of antenna mount designs, structural analysis, cable routing and permit drawings. During development of the project, the antenna mounting location changed, requiring K2 to revise the permit plans before construction could proceed.

What made this project difficult or unusual?

  • Antenna mounts had to be engineered specifically for the building.
  • The supporting structure had to be evaluated as part of the mount-design process.
  • The antenna mounting location changed after the original engineering work due to building owner approvals, requiring revised permit documents.
  • RF cable routing, building penetration, grounding and antenna mounting all had to be coordinated.
  • Approximately 1,000 feet of coaxial cable had to be routed between the antennas and interior equipment.
  • Permitting, submission and inspections were incorporated into the construction phase.
  • A manlift was required to perform portions of the installation.

3. K2’s Solution

What did K2 actually do?

K2 approached the project as an integrated engineering and construction assignment rather than simply supplying and mounting antennas.

The initial phase included an engineering site inspection to gather field data, development of antenna mounting designs and structural analysis, and preparation of permit drawings showing the site configuration, mounting details, cable routing and electrical one-line information.

When the mounting location subsequently changed, K2 revised the permit plans and proceeded with the field installation. The construction scope included antenna mounts, antennas, approximately 1,000 feet of coaxial cable, a building entry port, grounding, line sweeping, permitting and inspections, and a photographic closeout package.

Key elements of the solution

  • Performed an on-site engineering survey and collected field data for antenna mount design.
  • Designed antenna-support mounting and evaluated the supporting structure.
  • Produced and later revised permit/construction drawings after the mounting location changed.
  • Furnished and installed the antenna mounting system, antennas, coaxial transmission lines, building entry system and grounding.
  • Tested the completed RF transmission lines and documented the finished installation.
  • Managed permit application, submission and inspections.
  • Coordinated field work, supervision and an antenna mockup.

Engineering involved

  • Site inspection and field verification.
  • Antenna mount design.
  • Supporting-structure analysis.
  • Cable-routing design.
  • Electrical/grounding one-line documentation.
  • Permit drawing preparation and revision.

Field/construction work involved

  • Installation of engineered antenna mounts.
  • Installation of three Discone antennas and one UHF/450 MHz antenna.
  • Installation of approximately 1,000 feet of 1/2-inch coaxial cable — approximately 250 feet per antenna.
  • Installation of an RF cable entry port.
  • Grounding of mast pipes to the facility’s main ground bus/building steel.
  • Sweep testing of installed transmission lines.
  • Manlift-supported installation.
  • Closeout photography and project documentation.

4. What Made K2’s Approach Different?

K2’s differentiator — draft

K2 was able to take responsibility for both the engineering and construction portions of the antenna project. Rather than requiring the customer to separately coordinate a structural engineer, permitting consultant, RF contractor and installation contractor, K2 handled the field survey, mount engineering, permit drawings and revisions, antenna and transmission-line installation, grounding, testing, permitting and project closeout.

That integrated capability became particularly important when the planned antenna location changed. K2 could revise the engineering and permit documentation and carry those changes directly into the construction phase instead of requiring the customer to coordinate changes among several independent contractors.

This is likely the central story for the finished case study.

5. Technical Complexity

Equipment / systems:

  • Building-mounted communications antenna system supporting WNBC/WNJU operations.

Antenna / RF:

  • Three Diamond Original D3000N Super Discone antennas.
  • One Sinclair SC366-HF2LDF (D00) antenna, identified in the quotation as a 450 MHz whip/UHF antenna.
  • Approximately 1,000 feet of 1/2-inch coaxial transmission line.
  • RF line sweep testing after installation.

Structural:

  • Custom antenna mount design.
  • Supporting-structure analysis.
  • 15-foot galvanized pipe.
  • Mounting brackets.
  • Crossover members.
  • Pipe mounts.
  • Wall anchors.

Electrical / grounding:

  • Grounding of antenna mast pipes.
  • Connection to the facility main grounding bus/building steel.
  • Electrical one-line incorporated into permit documents.

Cabling / transmission lines:

  • Four antenna transmission lines.
  • Approximately 250 feet per antenna.
  • Approximately 1,000 feet total.
  • Building entry port.
  • Final sweep testing.

Permitting / compliance:

  • Original permit drawings.
  • Revised permit drawings following relocation of the antenna mounting position.
  • Permit application and submission.
  • Required inspections.

Special equipment / access:

  • Manlift.

Other technical considerations:

  • Antenna mockup performed as part of coordination/supervision.
  • Construction closeout photo package.
  • Structural drawings were requested for review during the engineering phase.

6. The Result

The quotations establish the intended scope of the completed system, but they do not document final field completion, schedule performance or final operating results. Those items should be confirmed from project closeout records before publication.

What the proposal establishes

  • 3 Discone antennas
  • 1 UHF/450 MHz antenna
  • 4 antenna transmission lines
  • Approximately 1,000 feet of coaxial cable
  • New antenna support/mounting infrastructure
  • New cable entry port
  • Grounding to the building grounding system
  • RF sweep testing
  • Permitting and inspections
  • Project closeout documentation

Items to confirm with Engineering / Project Management

TO CONFIRM Was the project completed exactly as quoted? yesFinal completion date. Final inspection was on 9/11/2025Whether all four antennas entered service. Not sure. The customer did not tell us.Whether the final cable length was approximately 1,000 feet. It was somewhat less, not sure exactly. Were there any unexpected structural or installation conditions? Finding the right mounting location that was acceptable to building management and WNBC/WNJU and then determining the cable path was a minor challenge. Were there changes required by Englewood during plan review or inspection? noDid K2 complete the project on the original construction schedule? There were delays in the fabrication of the mount materials and the whip antenna. Was there any interruption to WNBC/WNJU operations? noDid K2 work around existing operational communications equipment? No, the existing antenna system was still operational on the building in Fort Lee, NJ that they were moving from.Were there any particularly difficult cable routes or building penetrations? The cable route had to be carefully planned to avoid other tenant spaces and existing interior obstacles.Did the antenna mockup solve a specific concern? It assured building management that the antennas would not be objectionable to the look of the building. Were there any RF performance targets or test results worth mentioning? No.

7. Why This Matters to a Potential Customer

Takeaway — draft

This project demonstrates K2 Communications’ ability to manage a building-mounted communications project from engineering through final installation. K2 combined antenna and RF expertise with structural analysis, permitting, specialized mounting, transmission-line installation, grounding, testing and field construction — and was able to accommodate a change in antenna location without forcing the customer to coordinate multiple specialty contractors.

The project is a strong example for prospective broadcasters, media companies, public-safety organizations, corporate communications facilities and other customers with mission-critical rooftop RF systems.

Quick Version for the Engineering Team

PROJECT: WNBC/WNJU Englewood Antenna Installation

CUSTOMER / INDUSTRY: WNBC/WNJU / Broadcast Television

LOCATION: 100 Forest Avenue, Englewood, NJ

1. What did the customer need?

Install a new building-mounted communications antenna system, including antennas, RF transmission lines, grounding, structural mounting and permitting.

2. What made it difficult?

The installation required engineered antenna mounting, structural review, permitting and approximately 250 feet of coax per antenna. The planned mounting location also changed after the initial engineering, requiring revised permit documents.

3. What did K2 do?

Surveyed the site, engineered the mounts, analyzed the supporting structure, prepared and revised permit drawings, installed antennas and RF cabling, installed the building entry and grounding system, handled permitting/inspections, sweep-tested the lines and provided closeout documentation.

4. What engineering was required?

Mount design, supporting-structure analysis, cable routing, mounting details, electrical/grounding one-line and permit drawings.

5. What specialized field work was required?

Antenna and mount installation, approximately 1,000 feet of coaxial cable installation, RF building entry, grounding, manlift work and RF sweep testing.

6. What problems did K2 have to solve?

TO CONFIRM: Why was the antenna location changed? Were there structural, access, RF, landlord or permitting issues that caused it?

7. What equipment / systems were involved?

Three Diamond D3000N Super Discone antennas, one Sinclair 450 MHz antenna, four coaxial transmission lines, custom support/mounting hardware, grounding system and RF entry port.

8. What was the result?

TO CONFIRM from project closeout records.

9. What makes this a good example of K2’s capabilities?

K2 combined RF, structural engineering, permitting and field construction under one contractor and adapted the engineering when the installation location changed.

10. What photos/drawings/documents do we have?

The proposal indicates that a closeout photo package was to be provided. Also look for the original and revised permit drawings, antenna mockup photos, installation photos and RF sweep reports.

Recommended next step: Confirm why the antenna location changed and what field problem K2 had to solve; that detail is likely to provide the strongest narrative hook for the final case study.