Author: jason

Englewood Cliffs Antenna Installation

K2 Communications Case Study

WNBC/WNJU Englewood Discone Antenna Installation

Draft prepared from K2 quotations dated March 31, 2025 and June 11, 2025. Items not documented in the quotations are marked “To Confirm.”

1. Project Overview

Project Name: WNBC/WNJU Englewood Discone Antenna Installation

Location: 100 West Forest Avenue, Englewood, New Jersey

Customer / Industry: WNBC / WNJU — Broadcast Television / Media

Project Type: Building-mounted communications antenna engineering, permitting and installation

Date / Year: 2025 — engineering phase quoted March 31, 2025; installation phase quoted June 11, 2025.

Primary K2 Services

☒ Antenna & Wireless Infrastructure

☒ Engineering, Permitting & Structural Modifications

☒ Tower Maintenance & Remediation

☒ Communications Equipment Decommissioning

☒ RF Cabling & Transmission Infrastructure

2. The Challenge

What did the customer need to accomplish?

As WNJU was going to be moving out of their Fort Lee location, they needed to establish communications antenna infrastructure at its new Englewood facility, prior to the decommissioning of the old site. This included antenna mounting, RF transmission lines, building entry, grounding and permitting.

The project began with an engineering site inspection and development of antenna mount designs, structural analysis, cable routing and permit drawings. During development of the project, the antenna mounting location changed, requiring K2 to revise the permit plans before construction could proceed.

What made this project difficult or unusual?

  • Antenna mounts had to be engineered specifically for the building.
  • The supporting structure had to be evaluated as part of the mount-design process.
  • The antenna mounting location changed after the original engineering work due to building owner approvals, requiring revised permit documents.
  • RF cable routing, building penetration, grounding and antenna mounting all had to be coordinated.
  • Approximately 1,000 feet of coaxial cable had to be routed between the antennas and interior equipment.
  • Permitting, submission and inspections were incorporated into the construction phase.
  • A manlift was required to perform portions of the installation.

3. K2’s Solution

What did K2 actually do?

K2 approached the project as an integrated engineering and construction assignment rather than simply supplying and mounting antennas.

The initial phase included an engineering site inspection to gather field data, development of antenna mounting designs and structural analysis, and preparation of permit drawings showing the site configuration, mounting details, cable routing and electrical one-line information.

When the mounting location subsequently changed, K2 revised the permit plans and proceeded with the field installation. The construction scope included antenna mounts, antennas, approximately 1,000 feet of coaxial cable, a building entry port, grounding, line sweeping, permitting and inspections, and a photographic closeout package.

Key elements of the solution

  • Performed an on-site engineering survey and collected field data for antenna mount design.
  • Designed antenna-support mounting and evaluated the supporting structure.
  • Produced and later revised permit/construction drawings after the mounting location changed.
  • Furnished and installed the antenna mounting system, antennas, coaxial transmission lines, building entry system and grounding.
  • Tested the completed RF transmission lines and documented the finished installation.
  • Managed permit application, submission and inspections.
  • Coordinated field work, supervision and an antenna mockup.

Engineering involved

  • Site inspection and field verification.
  • Antenna mount design.
  • Supporting-structure analysis.
  • Cable-routing design.
  • Electrical/grounding one-line documentation.
  • Permit drawing preparation and revision.

Field/construction work involved

  • Installation of engineered antenna mounts.
  • Installation of three Discone antennas and one UHF/450 MHz antenna.
  • Installation of approximately 1,000 feet of 1/2-inch coaxial cable — approximately 250 feet per antenna.
  • Installation of an RF cable entry port.
  • Grounding of mast pipes to the facility’s main ground bus/building steel.
  • Sweep testing of installed transmission lines.
  • Manlift-supported installation.
  • Closeout photography and project documentation.

4. What Made K2’s Approach Different?

K2’s differentiator — draft

K2 was able to take responsibility for both the engineering and construction portions of the antenna project. Rather than requiring the customer to separately coordinate a structural engineer, permitting consultant, RF contractor and installation contractor, K2 handled the field survey, mount engineering, permit drawings and revisions, antenna and transmission-line installation, grounding, testing, permitting and project closeout.

That integrated capability became particularly important when the planned antenna location changed. K2 could revise the engineering and permit documentation and carry those changes directly into the construction phase instead of requiring the customer to coordinate changes among several independent contractors.

This is likely the central story for the finished case study.

5. Technical Complexity

Equipment / systems:

  • Building-mounted communications antenna system supporting WNBC/WNJU operations.

Antenna / RF:

  • Three Diamond Original D3000N Super Discone antennas.
  • One Sinclair SC366-HF2LDF (D00) antenna, identified in the quotation as a 450 MHz whip/UHF antenna.
  • Approximately 1,000 feet of 1/2-inch coaxial transmission line.
  • RF line sweep testing after installation.

Structural:

  • Custom antenna mount design.
  • Supporting-structure analysis.
  • 15-foot galvanized pipe.
  • Mounting brackets.
  • Crossover members.
  • Pipe mounts.
  • Wall anchors.

Electrical / grounding:

  • Grounding of antenna mast pipes.
  • Connection to the facility main grounding bus/building steel.
  • Electrical one-line incorporated into permit documents.

Cabling / transmission lines:

  • Four antenna transmission lines.
  • Approximately 250 feet per antenna.
  • Approximately 1,000 feet total.
  • Building entry port.
  • Final sweep testing.

Permitting / compliance:

  • Original permit drawings.
  • Revised permit drawings following relocation of the antenna mounting position.
  • Permit application and submission.
  • Required inspections.

Special equipment / access:

  • Manlift.

Other technical considerations:

  • Antenna mockup performed as part of coordination/supervision.
  • Construction closeout photo package.
  • Structural drawings were requested for review during the engineering phase.

6. The Result

The quotations establish the intended scope of the completed system, but they do not document final field completion, schedule performance or final operating results. Those items should be confirmed from project closeout records before publication.

What the proposal establishes

  • 3 Discone antennas
  • 1 UHF/450 MHz antenna
  • 4 antenna transmission lines
  • Approximately 1,000 feet of coaxial cable
  • New antenna support/mounting infrastructure
  • New cable entry port
  • Grounding to the building grounding system
  • RF sweep testing
  • Permitting and inspections
  • Project closeout documentation

Items to confirm with Engineering / Project Management

TO CONFIRM Was the project completed exactly as quoted? yesFinal completion date. Final inspection was on 9/11/2025Whether all four antennas entered service. Not sure. The customer did not tell us.Whether the final cable length was approximately 1,000 feet. It was somewhat less, not sure exactly. Were there any unexpected structural or installation conditions? Finding the right mounting location that was acceptable to building management and WNBC/WNJU and then determining the cable path was a minor challenge. Were there changes required by Englewood during plan review or inspection? noDid K2 complete the project on the original construction schedule? There were delays in the fabrication of the mount materials and the whip antenna. Was there any interruption to WNBC/WNJU operations? noDid K2 work around existing operational communications equipment? No, the existing antenna system was still operational on the building in Fort Lee, NJ that they were moving from.Were there any particularly difficult cable routes or building penetrations? The cable route had to be carefully planned to avoid other tenant spaces and existing interior obstacles.Did the antenna mockup solve a specific concern? It assured building management that the antennas would not be objectionable to the look of the building. Were there any RF performance targets or test results worth mentioning? No.

7. Why This Matters to a Potential Customer

Takeaway — draft

This project demonstrates K2 Communications’ ability to manage a building-mounted communications project from engineering through final installation. K2 combined antenna and RF expertise with structural analysis, permitting, specialized mounting, transmission-line installation, grounding, testing and field construction — and was able to accommodate a change in antenna location without forcing the customer to coordinate multiple specialty contractors.

The project is a strong example for prospective broadcasters, media companies, public-safety organizations, corporate communications facilities and other customers with mission-critical rooftop RF systems.

Quick Version for the Engineering Team

PROJECT: WNBC/WNJU Englewood Antenna Installation

CUSTOMER / INDUSTRY: WNBC/WNJU / Broadcast Television

LOCATION: 100 Forest Avenue, Englewood, NJ

1. What did the customer need?

Install a new building-mounted communications antenna system, including antennas, RF transmission lines, grounding, structural mounting and permitting.

2. What made it difficult?

The installation required engineered antenna mounting, structural review, permitting and approximately 250 feet of coax per antenna. The planned mounting location also changed after the initial engineering, requiring revised permit documents.

3. What did K2 do?

Surveyed the site, engineered the mounts, analyzed the supporting structure, prepared and revised permit drawings, installed antennas and RF cabling, installed the building entry and grounding system, handled permitting/inspections, sweep-tested the lines and provided closeout documentation.

4. What engineering was required?

Mount design, supporting-structure analysis, cable routing, mounting details, electrical/grounding one-line and permit drawings.

5. What specialized field work was required?

Antenna and mount installation, approximately 1,000 feet of coaxial cable installation, RF building entry, grounding, manlift work and RF sweep testing.

6. What problems did K2 have to solve?

TO CONFIRM: Why was the antenna location changed? Were there structural, access, RF, landlord or permitting issues that caused it?

7. What equipment / systems were involved?

Three Diamond D3000N Super Discone antennas, one Sinclair 450 MHz antenna, four coaxial transmission lines, custom support/mounting hardware, grounding system and RF entry port.

8. What was the result?

TO CONFIRM from project closeout records.

9. What makes this a good example of K2’s capabilities?

K2 combined RF, structural engineering, permitting and field construction under one contractor and adapted the engineering when the installation location changed.

10. What photos/drawings/documents do we have?

The proposal indicates that a closeout photo package was to be provided. Also look for the original and revised permit drawings, antenna mockup photos, installation photos and RF sweep reports.

Recommended next step: Confirm why the antenna location changed and what field problem K2 had to solve; that detail is likely to provide the strongest narrative hook for the final case study.

Plainview Guyed Tower Inspection & Repairs

K2 COMMUNICATIONS CASE STUDY WLIW Plainview Guyed Tower Inspection & Corrective Maintenance Plainview, New York
WLIW Plainview guyed towerPROJECT AT A GLANCE Customer / Industry
WNET / WLIW — Broadcast Communications Structure
266-ft guyed tower; highest appurtenance at 306 ft Condition Assessment
August 13, 2024 Corrective Work
December 19, 2024 Engineer Sign-Off
January 27, 2025 Reference Standard
ANSI/TIA-222-H Annex J maintenance and inspection procedures K2 Role
Inspection coordination, corrective work scope, tower remediation, decommissioning, and closeout coordination

From standards-based condition assessment to documented corrective work and engineering closeout.

1. PROJECT OVERVIEW

WNET engaged K2 Communications for a climbing inspection and TIA condition assessment of the WLIW Plainview tower. K2 coordinated the inspection and report process for the active 266-foot guyed structure, then developed the corrective-maintenance scope needed to address the documented deficiencies.

PRIMARY K2 SERVICES ■  Tower Maintenance & Remediation ■  Engineering / Inspection Coordination ■  Communications Equipment DecommissioningSUPPORTING SCOPE ■  Guy System & Grounding Corrections ■  Safety-Climb System Repairs ■  RF / Broadcast Shutdown Coordination

2. THE CHALLENGE

What did the customer need to accomplish?

The owner needed an objective, standards-based assessment of an in-service broadcast tower and a practical repair program that could move directly from findings to field correction. Because tower climbing required broadcast antennas to be turned down, inspection and repair activity also had to be coordinated around operational constraints.

What did the inspection find?

The August 2024 TIA-222-H Annex J assessment found the tower to be in good overall condition, but documented 17 maintenance deficiencies spanning the safety-climb system, guy tension and hardware, corrosion, grounding, abandoned coaxial cable, and unused lighting conduit. The findings included two Immediate Priority items, two Medium Priority items, and thirteen Low Priority items.

KEY INSPECTION THEMES
Safety climb • guy tension / hardware • corrosion control • anchor grounding • turnbuckle safety wire • abandoned coax / carrier hardware

Why was the work technically sensitive?

  • The structure was an active guyed broadcast tower with multiple antenna and transmission-line systems at several elevations.
  • Guy-system work had to preserve acceptable tension, twist, and plumb while correcting hardware and safety deficiencies.
  • Grounding corrections affected multiple anchor locations and had to align with tower-maintenance and lightning-protection requirements.
  • The safety-climb system extended essentially the full height of the tower and included both installation and corrosion issues.

3. K2’S SOLUTION

What did K2 actually do?

K2 converted the inspection findings into a defined corrective-work package and coordinated the field remediation and closeout. The repair proposal addressed checklist items 1 through 5 and 7 through 17, plus the separate removal of abandoned T-Mobile coaxial cable and associated light-rust touch-up work.

Inspection & engineering coordination: Coordinated the climbing inspection and TIA-222-H condition assessment process.

  • Used the engineer’s priority-ranked findings and recommendations to build the repair scope and closeout requirements.

Safety-climb system: Corrected the top connection and other safety-climb deficiencies.

  • Replaced the safety-climb cable from approximately 10 ft to 250 ft and addressed corrosion / top-assembly conditions above that level.

Guy system & hardware: Adjusted out-of-range guy tension to an acceptable range.

  • Addressed corroded shackle and cotter-pin hardware, missing mousing, improper wire serving, and turnbuckle safety-wire routing / sizing.

Grounding & corrosion control: Installed anchor fan-plate grounding, corrected improper guy-tail grounding, and addressed corroded grounding clips.

  • Treated lightly corroded mount members / hardware with zinc-rich protective coating where specified.

Decommissioning & cleanup: Removed abandoned coaxial cable and associated unused equipment identified for removal.

  • Addressed corrosion on unused lighting-system conduit and other punch-list items.

Examples from inspection and repair closeout

Inspection finding: corroded safety-climb top assembly Closeout documentation: corrected top safety-climb connection
Closeout documentation: anchor fan-plate grounding installed Closeout documentation: turnbuckle safety-wire correction

4. WHAT MADE K2 DIFFERENT

This project was not treated as a report-only inspection. K2 carried the work from assessment through repair scoping, field execution coordination, photo documentation, and engineering closeout — giving the customer a single, practical path from identified deficiency to verified correction.

  • Inspection findings were translated directly into a repair scope instead of being left as a stand-alone engineering report.
  • K2 coordinated across the broadcaster, engineering reviewers, and tower field crews while working around RF shutdown requirements.
  • The repair program combined climber-safety work, guy-system maintenance, grounding, corrosion control, decommissioning, and documentation in one coordinated effort.

5. TECHNICAL COMPLEXITY

  • 266-ft guyed tower with the highest appurtenance at 306 ft and multiple antenna / line systems at several elevations.
  • Safety-climb system deficiencies extending from approximately 10 ft through the top of the tower.
  • Guy-system corrections involving tension, shackles, cotter pins, mousing, wire serving, and turnbuckle safety wire.
  • Multiple anchor-grounding deficiencies requiring correction at AA, BB, and CC anchor locations.
  • Corrosion remediation on mount hardware and other tower accessories, plus removal of abandoned coaxial cable.
  • Operational coordination because broadcast antennas had to be turned down during climbing activity.

6. THE RESULT

Field repairs were completed on December 19, 2024. Repair photographs were submitted for engineering review, and Tectonic Engineering issued a January 27, 2025 sign-off confirming that the required maintenance items had been completed. The sign-off concluded that the tower repair work met industry standards and that the structure was in compliance with the Tower Maintenance guidelines of ANSI/TIA-222-H.

DOCUMENTED CLOSEOUT
All 17 assessment items were closed through repair documentation and engineering review. Tectonic also recommended a TIA inspection every three years, including verification of guy-wire condition, tower twist, and plumb geometry against design values.

7. WHY THIS MATTERS TO A POTENTIAL CUSTOMER

Tower owners often need more than an inspection report. They need a team that can identify the work, organize the corrective scope, coordinate qualified field resources, manage operating constraints, and deliver a clear closeout package. This project demonstrates K2’s ability to connect those steps into one accountable maintenance program for active communications infrastructure.

Source documentation used for this case study: K2 inspection and repair proposals; Delta Oaks Group TIA-222-H Maintenance and Condition Assessment Report; Tectonic Engineering sign-off letter.

Alpine Tower Microwave Install

Alpine Tower Microwave Antenna Installation

Two 6-foot microwave systems integrated into an existing 400-foot communications tower

Installed 6-foot microwave antenna, tower-mounted radio, custom mount and ice shield at the Alpine Tower.

LOCATION Alpine, New JerseyCUSTOMER New York Power Authority /
TRC
PROJECT TYPE Microwave infrastructureCOMPLETION April 2023

Project Overview

K2 Communications was engaged by New York Power Authority / TRC to support the installation of two new 6-foot microwave antenna systems on the 400-foot self-supporting Alpine Tower in Alpine, New Jersey. The project combined structural engineering, custom mount design, permitting, tower installation, RF cabling, grounding, electrical work, ice protection and final path alignment into a coordinated field effort.

PRIMARY K2 SERVICES

■ Antenna & wireless infrastructure

■ Engineering, permitting & structural coordination

■ Custom tower mounts

■ RF cabling & grounding

■ Electrical coordination

■ Microwave path alignment

The Challenge

NYPA required two new point-to-point microwave paths to be added to an existing, heavily developed communications tower. Each new 6-foot dish required a purpose-designed leg mount, tower-mounted outdoor radio equipment, transmission lines, grounding and ice protection at a high-elevation location.

INSTALLATION300-FOOT LOCATION355-FOOT LOCATION
Tower legNorth legEast leg
AntennaCommscope USX6-6GR, 6 ftCommscope USX6-6GR, 6 ft
Azimuth56.632°175.912°
Path length9.569 miles11.87 miles
FeedlinesTwo CNT-400 runsTwo CNT-400 runs
ProtectionIce shield above dishIce shield above dish

Engineering and Mount Design

Before construction, K2 coordinated a structural analysis of the existing tower using the proposed dishes, ODUs, feedlines and ice shields as the final loading condition. The analysis determined that the tower would meet TIA-222-H and the 2018 New Jersey Building Code with the new NYPA equipment installed, allowing the project to proceed without major structural reinforcement.

Custom mounts were engineered separately for the 300-foot and 355-foot locations, including tower clamps, mounting pipes, tie-back members and hot-dip-galvanized structural steel components. The 355-foot arrangement was revised to suit the final field configuration.

Engineering drawing showing the two dish elevations and custom mount configurations at 300 ft and 355 ft.

The K2 Solution

Tower installation — K2 coordinated and supervised installation of the two 6-foot microwave antennas, their tower-mounted ODUs/radios, custom mounts and ice shields at approximately 300 and 355 feet.

RF cabling and grounding — Two CNT-400 runs were installed to each antenna using the tower cable-support system. The design included coaxial surge protection and grounding kits at the top, midpoint and base of the tower runs.

Electrical infrastructure — A dedicated 240-volt, 20-amp circuit and submetering were provided for the microwave equipment.

Microwave alignment — The antennas served separate paths, so alignment work was performed on separate days to coordinate with the corresponding remote sites and establish the required links.

Permitting and closeout — K2 coordinated structural documentation, permit drawings, construction supervision and municipal inspection. Building and electrical approvals were completed in April 2023.

The Result

The completed project added two microwave communications paths to the Alpine Tower while making use of the existing structure and site infrastructure. K2 provided the engineering coordination, custom mounting solution, field installation, RF cabling, grounding, electrical coordination, ice protection and antenna alignment needed to bring the systems into service.

DELIVERED SYSTEM ■ Two 6-foot microwave antennas at approximately 300 ft and 355 ft ■ Tower-mounted microwave ODUs/radios and custom leg mounts ■ Four CNT-400 transmission-line runs with grounding and surge protection ■ Two antenna ice shields ■ Dedicated electrical service and submetering ■ Final microwave path alignment

Project Significance

This project demonstrates K2 Communications’ ability to manage a microwave infrastructure project from engineering through final installation. By combining structural analysis, custom mount engineering, permitting, tower construction, RF cabling, electrical coordination and precision antenna alignment under a single project-management effort, K2 integrated two substantial microwave systems onto an existing 400-foot communications tower without the need for major tower reinforcement. Completed microwave installation.

Project documentation: K2 Communications quotations and project drawings; Towerkraft Engineering structural certification and mount drawings; municipal inspection records.

Temple University Beauty Camera

NBC10 / Telemundo62

Temple University Beauty/Weather Camera Installation

Morgan Hall | Philadelphia, Pennsylvania | Completed March 17, 2026

A structurally engineered, non-penetrating rooftop camera system with protected Cat6 infrastructure on an occupied high-rise residence.

1. Project Overview

K2 Communications installed a remotely operated rooftop beauty/weather camera for NBC10 and Telemundo62 on Morgan Hall at Temple University. The camera provides both stations with a high-elevation position primarily overlooking the Philadelphia skyline for weather coverage, live backgrounds and other broadcast applications. The project combined structural engineering, a ballasted non-penetrating rooftop mount, approximately 200 feet of protected communications cabling, interior equipment installation and coordination with building management and security.LOCATION
Morgan Hall, Temple University, Philadelphia, PA CUSTOMER
NBC10 / Telemundo62 PROJECT TYPE
Rooftop remote beauty/weather camera COMPLETED
March 17, 2026 CAMERA
Canon CR-X300

2. The Challenge

NBC10 / Telemundo62 needed a permanent rooftop camera location with a clear Philadelphia skyline view. Morgan Hall provided the elevation and sightline, but the camera had to be installed on the penthouse roof without compromising the existing roof membrane and while accounting for significant wind loading.

Because Morgan Hall is an occupied student residence, access, security and noise also had to be managed carefully. K2 coordinated rooftop access with the building engineer and worked with management and security to minimize disruption to residents and normal building operations.

Before – selected rooftop camera locationCompleted installation – ballasted non-penetrating mount

3. K2’s Solution

K2 developed and coordinated a complete rooftop installation built around a Baird non-penetrating ballasted mount and a protected communications pathway from the camera to an interior equipment closet one floor below.

  • Coordinate structural engineering and roof-loading analysis for the proposed camera and mount.
  • Supply and install the non-penetrating rooftop mount and engineered ballast.
  • Install the Canon CR-X300 remote camera at the top of the approximately 10-foot mast system.
  • Install two Cat6 cable runs – approximately 200 feet – in PVC conduit across the roof.
  • Support the rooftop conduit on a sleeper system to protect the roof membrane.
  • Route the Cat6 into a communications closet one floor below and install the associated equipment cabinet.
  • Provide project management, field supervision and coordination with building personnel and security.

4. Engineering & Technical Complexity

114 MPH ULTIMATE DESIGN WIND SPEED495 LB ENGINEERED CMU BALLAST~200 FT DUAL CAT6 ROUTE
Structural standardASCE 7-16 / applicable Pennsylvania building code criteria
Ballast configurationApprox. 198 lb front tray + 297 lb rear tray
Total installation weightApprox. 725 lb including mount, ballast and equipment
Calculated roof pressure16.4 psf versus 20 psf design live load
Mount component utilizationMount pipe 27%; kicker assembly 36%; base frame 13% – all pass
CameraCanon CR-X300 remote camera

Planning sketch showing the rooftop camera location and conduit route to the building interior.

5. Protecting the Roof and Infrastructure

The rooftop installation was designed to avoid penetrations through the existing roof. The camera mount uses ballast to resist sliding and overturning, with protective material beneath the base. The engineering analysis determined that the resulting roof pressure remained below the roof’s design live load.

The communications route received the same attention. Two Cat6 cables were installed in PVC conduit and supported on a sleeper system rather than laid directly on the roofing surface. This protected the roof membrane while providing a durable pathway for the approximately 200-foot run to the equipment closet one floor below.

6. Site Access & Coordination

Morgan Hall is a student residence, so security, access and noise were important project constraints. K2 coordinated with the building engineer, management and security to schedule and control access to the work areas.

The electrical contractor transported the materials to the roof, eliminating the need for a crane or specialized lifting equipment. A collapsible ladder, similar to a Little Giant, was used to reach the elevated camera during installation and final work. No significant field changes to the engineered design were required.

7. The Result

The installation was completed on March 17, 2026 and is in service for both NBC10 and Telemundo62. The finished system provides a permanent, remotely operated camera position with expansive views toward the Philadelphia skyline while meeting the building’s structural, roofing and operational requirements.

COMPLETED SYSTEM Canon CR-X300 remote beauty/weather cameraApprox. 10-foot non-penetrating rooftop mountSite-specific structural and wind-load engineeringApprox. 495 lb engineered ballastApprox. 200 ft of dual Cat6 in sleeper-supported PVC conduitInterior communications equipment cabinet

8. Why This Project Matters

A rooftop broadcast camera may appear straightforward, but successful installations require structural loading, wind forces, roof integrity, cable routing, access and building operations to work together. The Temple University project demonstrates K2 Communications’ ability to coordinate those disciplines – from engineering and mount selection through field installation and communications infrastructure – to turn a rooftop location into a practical broadcast facility.

K2 Communications, LLC | Broadcast and Communications Infrastructure

ATSC 3.0 Over Fiber & Cat6

NBC New York
ATSC 3.0 Distribution over Fiber

30 Rockefeller Plaza, New York, NY
Testing at Alpine Tower, Alpine, NJ

K2 Communications tested ATSC 3.0 NextGen TV signal transport for NBC New York’s new production facility at 30 Rockefeller Plaza, then installed the fiber equipment and adjusted signal levels on site. Successful testing at Alpine Tower supported the equipment purchase and deployment, including 26 Zinwell set-top boxes installed by NBC.

Project challenge

NBC needed to carry off-air television signals from its rooftop reception system to the second floor and distribute them to monitors over shielded Cat6a cable. With anticipated cable runs reaching approximately 350 feet, the engineering task was to establish whether the complete signal path could preserve sufficient signal quality for reliable ATSC 3.0 decoding.

The proposed system used the building’s existing dark fiber for vertical transport, followed by Muxlab CATV distribution hubs and baluns for the final cable runs. K2 evaluated the RF signal through each stage, including the losses introduced by longer Cat6a runs.

Testing at Alpine Tower

K2 assembled a representative signal path using a Televes Ellipse Mix antenna mounted approximately 110 feet above ground on Alpine Tower, with about 150 feet of RG-6 coax feeding the test equipment. A Televes 238201 FiberKom transmitter and 238101 receiver were connected through a one-meter single-mode optical jumper. The receiver fed a Muxlab 16-port CATV hub, shielded Cat6a cable, a CATV balun and a Zinwell ZAT-600B decoder connected to a monitor by HDMI.

Using a Rover Tab 7 Ultra analyzer and the decoder’s reported readings, K2 measured signal levels and checked picture, sound and decoder lock at multiple cable lengths. Testing focused on UHF RF channel 32 at 581 MHz, carrying WNBC’s NextGen TV service, and included VHF RF channel 11 at 201 MHz. Measurements were recorded on December 17 and 27, 2024.

Testing established the deployment approach

The decoder remained locked on both tested channels through 386 feet of Cat6a. At that length, measured cable loss relative to a six-foot jumper was 60.0 dB on UHF channel 32 and 34.8 dB on VHF channel 11. A 750-foot UHF test did not maintain lock, establishing a practical limit within the tested configurations.

Measured performance at Alpine

Cat6a lengthCh 32 cable lossCh 11 cable lossDecoder lock
256 ft40.1 dB22.9 dBBoth channels
326 ft51.4 dB30.7 dBBoth channels
386 ft60.0 dB34.8 dBBoth channels

Cable losses are relative to the six-foot Cat6a reference jumper in K2’s December 27, 2024 report. These are test results, not measurements of the installed building cabling.

The test receiver used its maximum attenuation setting to avoid overdriving the RF output on the short optical link. K2’s survey found a stronger, clean off-air signal at 30 Rockefeller Plaza than at Alpine. These findings supported proceeding with the installation and setting receiver levels to suit the actual building signal path.

Equipment procurement and installation

Following the successful test report, K2 purchased the fiber and distribution equipment. The January 2025 procurement records include a Televes 238201 transmitter, four Televes 238101 receivers, Muxlab CATV hubs and shielded baluns, coaxial splitters and equipment shelves. A separate January 30, 2025 purchase order covered 26 Zinwell NextGen TV set-top boxes.

The distribution plan placed the fiber transmitter at the existing 66th-floor fiber shelf, used existing dark fiber and the seventh-floor fiber distribution split, and located optical receivers at second-floor IDF shelves. The receivers restored the RF signals for distribution through the CATV hubs and Cat6a connections to the decoder locations.

K2 installed the fiber equipment at 30 Rockefeller Plaza and adjusted signal levels on site to match the installed distribution path. NBC installed the Zinwell set-top boxes. This division of work connected K2’s transport-system testing and installation with NBC’s deployment of the receiving equipment in the new production facility.

Project outcome

K2 moved the project from a tested signal path to an installed fiber transport system, providing NBC with a measured basis for distributing NextGen TV signals to the new facility. The work combined off-air reception assessment, RF-over-fiber testing, extended Cat6a evaluation, equipment procurement and on-site level adjustment.

Project records: K2 test report and distribution diagram dated December 27, 2024; October and December 2024 proposals; purchase orders 700220, 700226 and 700227. Installation responsibilities reflect the project completion account supplied by K2.

First Horizon Bank

First Horizon Bank

Rooftop Antenna Relocation

800 South Gay Street | Knoxville, Tennessee

Four rooftop antenna frames and cable routes surrounding the penthouse. Permit drawing S-100, Revision 3.

Engineered antenna relocation to accommodate replacement of the four-sided penthouse sign.

1. PROJECT OVERVIEW

K2 Communications developed an engineered relocation solution for antennas mounted on the rooftop penthouse of the First Horizon Bank building. Replacement of the sign on all four faces of the penthouse required moving the antennas to independent supports on the main roof, with new cable routes and coordinated transitions for multiple communications users.

2. THE CHALLENGE

The penthouse supported a mix of microwave dishes, satellite antennas, panels, and omnidirectional antennas. Moving this equipment required more than clearing the sign contractor’s work area: the new arrangement had to address antenna orientation, structural support, cable lengths, grounding, roof protection, and maintenance access. Coordination with equipment owners was essential to plan service transitions around the building improvements.

3. STRUCTURAL SUPPORT AND ROOFTOP LAYOUT

The permit design placed four gravity-mounted steel antenna frames around the main roof, one in each sector surrounding the penthouse. The frames incorporated mounting pipes, horizontal rails, and diagonal bracing, with rubber mats beneath the steel bases to protect the roof. The antenna schedule identified equipment assignments, mounting elevations, and cable requirements for the proposed locations.

4. CABLE ROUTING AND ROOF ACCESS

Four rooftop cable-tray routes connected the penthouse to the new frames. Supported trays organized the cable runs, while steel step-overs maintained access across them. The design also required connection to the existing grounding system, with its condition checked and upgrades made as necessary.

5. K2 SCOPE AND COORDINATION

  • Engineering coordination and signed, sealed permit drawings for the rooftop relocation.
  • Removal and demolition work, followed by procurement and installation planning for the new frames, cable trays, and associated hardware.
  • Antenna-owner coordination, replacement or extended cabling, and sequencing of equipment moves to the new supports.
  • Comparison of a direct move to permanent locations with a temporary-then-permanent relocation approach.
  • Project scheduling linking plan approval, permitting, material delivery, frame installation, equipment relocation, and permit closeout.

6. PROJECT VALUE

The engineered layout separated the antenna supports from the penthouse sign structure and established permanent equipment locations around the roof. It provided a coordinated basis for the sign replacement while addressing the structural, cabling, and access needs of a rooftop shared by multiple communications users.

Venture Technologies at Alpine Tower

Venture Technologies Group

Low Power TV Station Installation at Alpine Tower

Alpine, New Jersey | 2019

Custom antenna mount assembly for the east tower leg at 270 feet. TowerKraft Engineering drawing 8420-VENTURE, sheet 2.

Structural engineering, permitting, antenna installation and electrical infrastructure for a new low power television station.

1. PROJECT OVERVIEW

K2 provided the engineering coordination, permitting, antenna and transmission-line installation, and electrical infrastructure for Venture Technologies Group’s low power television station at Alpine Tower. The project supported W28ET-D on RF Channel 28, integrating a new broadcast antenna with the existing tower and preparing the equipment location for the customer’s transmitter installation.

2. THE CHALLENGE

The installation required more than mounting an antenna. The tower needed evaluation for the added load, a custom interface was needed for the existing east leg, and rooftop steel dunnage required analysis for a heat exchanger and 45 kVA transformer. Construction documents and electrical distribution had to address the antenna, transmitter, and cooling equipment as a coordinated installation.

3. STRUCTURAL ENGINEERING AND MOUNT DESIGN

K2’s engineering scope included a structural model run of Alpine Tower with the proposed ERI ALP4L-ESBR-28 antenna, together with analysis of the existing rooftop dunnage for the transformer and heat exchanger. The antenna interface design was developed separately, with shop drawings detailing its connection to the tower.

TowerKraft Engineering’s drawings placed the antenna centerline at 270 feet on the east leg of the 400-foot tower. The mounting assembly used custom inside and outside clamp weldments and a 2½-inch Schedule 40 pipe, 10 feet 6 inches long. Fabrication notes called for steel with a minimum 36 ksi yield strength and hot-dip galvanizing to ASTM A123 or A153. The tower drawing identified TIA-222-G as the design standard.

4. CONSTRUCTION DRAWINGS AND PERMITTING

K2 coordinated an engineering site visit to document existing conditions and proposed equipment locations. The drawing scope included antenna, transmitter, and heat-exchanger construction drawings, an electrical one-line diagram, and signing and sealing by a New Jersey professional engineer, using the customer’s system design as the basis.

K2 also coordinated the permit application. Construction permit 19-099, issued July 29, 2019, authorized building and electrical work at 293 US Route 9W in Alpine, with the work described as “Venture Tech Group Antenna etc.”

30 Rock Rooftop Antenna Consolidation

Rooftop Antenna Consolidation & RF System Relocation

K2 COMMUNICATIONS, LLC

CASE STUDY

Tishman Speyer / 30 Rockefeller Plaza

Rooftop Antenna Consolidation & RF System Relocation

New York, New York | August 2021 – September 2024

A multi-year RF, structural and construction program that consolidated rooftop communications while preserving critical field coverage and improving the observation-deck skyline.
K2 COMMUNICATIONS, LLCCASE STUDY

1. Project Overview

As part of a major redevelopment of the observation deck at 30 Rockefeller Plaza, Tishman Speyer sought to remove the visual clutter created by numerous whip antennas mounted on the 70th-story main bulkhead and elevator penthouse. Many of the antennas supported active NBC communications with field personnel and camera crews, so they could not simply be removed. K2 was engaged to develop a lower-profile solution that would preserve practical communications coverage while coordinating RF design, structural engineering, permitting and construction in an active high-rise environment.LOCATION
30 Rockefeller Plaza, New York, NY CUSTOMER
Tishman Speyer STAKEHOLDERS
NBC and other government / city communications users PROJECT TYPE
Rooftop RF relocation and antenna consolidation PROJECT DURATION
August 2021 – September 2024 RF SYSTEMS
Primarily 450 MHz UHF plus VHF services

2. The Challenge

The rooftop had accumulated a dense collection of whip antennas, dishes and support structures over time. New visitor attractions on the observation deck made the appearance of the roof much more important, but the remaining systems still had to perform reliably in a difficult urban RF environment.

The project therefore had to balance several competing requirements: maintaining communications service and coverage, reducing the visible antenna profile, working around active systems, accommodating multiple users, and developing structural solutions that could be installed and permitted within the constraints of the existing building.

Existing elevator penthouse and rooftop whip antennas. Existing antenna infrastructure viewed from the observation deck. Dense antenna mounting at the top of the existing penthouse.

C-Band Re-Allocation: We’re here to help.

Over the last year, The Federal Communications Commission (FCC) has been preparing for a major reallocation of spectrum in the C-Band. The proposal highlights efforts to have the 3.45-3.55 GHz spectrum ready for 5G implementation across the country. Auctions of the re-purposed spectrum will begin in December of 2020. Migration must be completed by December of 2023. When the re-allocation is complete, the Satellite Downlink portion of the C-Band spectrum will be reduced from 500 MHz to just 200 MHz.

Purpose of the Reallocation

This proposal supports FCC’s planned 5G implementation alongside other efforts such as an upcoming auction for the C-Band spectrum.. It is the FCC’s opinion that clearing this band for 5G use will close the United States’ Gap in 5G coverage by providing mid-range coverage.  This mid-range band is ideal for medium distance communications providing medium throughput. Higher band frequencies provide greater capacity over shorter distances, while lower bands provide lower capacity over long distance.

Future 5G networks will consist of mixed topologies. Very small cells operating at high frequencies will provide users within a few hundred feet with download speeds equaling or surpassing WiFi. These access points will be ideal for high density user environments, such as parks, stadiums, and airports, but require line-of-site to the end user.

Medium cells operating in the mid-band will provide more-mobile users with WiFi like throughput further away from the access point. The Mid-Band has greater penetration through materials like glass, leaves, and sheetrock than do higher frequencies. These frequencies also experience less rain fade.

Macro cells will continue to operate lower spectrum frequencies to provide users with 4G like throughput at longer distances and where line-of-site is not possible.

Impact on Satellite Communications

The C-Band consists of frequencies from 3.7MHz to 4.2MHz. Satellites have been operating in the C-Band for about 50 years. Most geosynchronous satellite services operating today make use of this band. The most common use of C-Band satellite services are television content distribution.

Many current C-Band operators will have to consolidate their services as the available C-Band downlink is effectively cut by almost two-thirds. In some cases, services can be moved to terrestrial fiber, but satellite is always the ideal choice for temporary or mobile uplinks (special events) or services in area with undeveloped or unreliable infrastructure. Fiber will never be able to serve ships at sea, which will always be dependent on satellite communications.

How can K2 Help?

K2 Communications has over 45 years’ experience in the integration of Broadcast technologies. We stand ready to help outfit your antennas for the upcoming 5G changes mandated by the FCC. We can assess your current allocation and identify channels that must be migrated within each time frame as indicated by the FCC order. We can help you plan for these migrations and provide required technology such as filters and low noise amplifiers.

K2 Communications also has a terrestrial IP-Based transmission system that may make up some of your lost satellite capacity and provide greater redundancy.  In test scenarios, we have helped our customers reduce their monthly operating cost by moving some critical traffic to fiber, freeing up costly satellite bandwidth.